Turnock Street Extension DA 'Slink'
image.png

Development Application for Turnock Street extension from the Turnock Street roundabout to Tweed Coast Road.
STATUS: SEARs ISSUED. TURNOCK EXTENSION DEED SIGNED WITH COUNCIL JULY 2022. DA BEING PREPARED IN 2023. COMMUNITY CONSULTATION BEING UNDERTAKEN IN Q3-4 2023

Altona FillDA2.PNG
North Altona Fill DA

Development Application for earthworks and drainage works - Altona Fill DA20/0965 moved north by 40m to enable Altona realignment and reflect approved extraction lake.

STATUS: SUBMITTED DEC 2021. LODGEMENT PROCESSED MARCH 2022. RFI RECEIVED OCTOBER 2022. CHANGE TO DA SUBMITTED 2023.

Altona Fill plan-.PNG
Altona Fill DA20/0965

Development Application to assist cattle grazing operations and future land fill operations.

STATUS: APPROVED. FILLING WORKS CONTINUTING THROUGHOUT 2023.

4.png
Turnock Fill & Haul Road CC DA05/0004.03 DWY 20/0250

Construction Certificate to enable Turnock Street Precinct to be filled consistent with approved DA 05/0004.03.
STATUS: DA APPROVED. CC LODGED. RFI PENDING. ON HOLD PENDING ALTERNATIVE OPTIONS TO FILL TURNOCK PRECINCT.

Haul Road overlay.JPG
Haul Road DA DA20/0860

Development Application for the western part of the Haul Road to transport fill to the approved Turnock Street Precinct.

STATUS: APPROVED. CONDITIONS OF CONSENT PROBLEMATIC TO EXECUTE APPROVAL. NOT PROGRESSED.​

Mega DA picture.PNG
Gales Southern Precincts Concept

Concept design for the construction of the New Link Road, filling to its north, filling west of Tweed Coast Road and relocation of Altona Road.
STATUS: MERGED INTO OVERALL MASTERPLAN CONCEPT DA IN PREPARATION IN 2023.

Quigan DA image.PNG
Quigan Street DA DA17/0554

Development Application for final land uses south south of Turnock Street including development, conservation and Quigan Park.

STATUS: ON HOLD PENDING OVERALL MASTERPLAN OUTCOME.